Replacement of a Dryer Drum in Gütersloh

Replacement of a Dryer Drum in Gütersloh

Heavy-Lift and Crane Logistics | Gütersloh | 2017

KDM organized the replacement of a dryer drum at the Unique Systems plant in Gütersloh. Both the old and new drums weighed approximately 250 metric tons each. Despite limited space, the planned operation was completed within one day.

The Project

The drying drum for wood chips was to be removed from the plant and replaced with a new one. Our scope of work included organizing the crane operations, transporting the drum on the factory grounds, and setting the old drum down in a designated area within the plant. The old drum remained on the grounds for the time being.

The Challenge

There was only about five meters of space between the plant and the adjacent building. During the lifting operation, a pipe bridge had to be taken into account; in addition, a shaft was still stuck in the old drum. In some places, there was only a few centimeters of clearance. The crane operator therefore had to rely on precise instructions from the signalers.

Our Solution

We organized the operation using two cranes for a tandem lift and a self-propelled transport platform. The old drum was lifted and moved sideways to guide it out of the plant. It was then transported on the platform and set down on the factory grounds. Afterward, the new drum was brought into the plant.

The result

The replacement was completed within one day, as scheduled. Afterward, only the usual finishing work was required.