Laboratory Modules for Wesemann Int. to Kigali
On behalf of Wesemann, KDM coordinated the logistics for shipping sensitive laboratory modules to Kigali. Production facilities in Germany, Ro-Ro shipping, low-vibration overland transport, and temporary storage in Rwanda ensured on-time delivery.
-
Two Boilers for the Heilbronn Power Plant
On behalf of SIK Peitz, KDM coordinated the logistics for the delivery of two boilers down to their foundations at the Heilbronn power plant. Despite low water levels, the agreed-upon delivery date was met—a prerequisite for timely commissioning.
-
Labormodule für Wesemann Int. nach Melbourne
Für Wesemann organisierte KDM den Transport sensibler Labormodule nach Melbourne. Ein Testaufbau mit elektrischen Kranen bereitete die Einbringung vor; Zwischenlagerung und Auslieferung wurden auf den Abruf des Endkunden abgestimmt.
-
Global Project Logistics consolidating Goods for a Water Treatment Plant
KDM coordinated worldwide shipments for Petro Techna for a water treatment plant in Saudi Arabia—ranging from packages and air freight to six large tanks on two partial charters.
-
20 MAN Chassis Shipped to Pakistan via the UAE
KDM coordinated the transport of 20 MAN chassis via Jebel Ali to Karachi. Temporary import, installation of the dump truck bodies, and re-export were integrated into a timely supply chain in collaboration with local partners.
-
Two Boilers for the Obernburg Power Plant
Two boilers, a narrow passage between two chimneys, and a drop-off point with no direct line of sight: KDM coordinated the installation at the Obernburg power plant. The chosen crane plan reduced on-site preparation and lifting operations to just a few days.
-
40 Emirates crew buses to Dubai
On behalf of Caetano, KDM transported 40 crew buses for Emirates from Portugal via Barcelona to Jebel Ali. The appropriate trailer capacity and a coordinated Ro-Ro transport ensured on-time delivery without any damage.
-
Two Industrial Steam Boilers in Bremen
KDM organized the unloading and transport of two steam boilers, each weighing approximately 70 metric tons, in Bremen. When the lifting jacks failed, the operation was quickly switched to two compact mobile cranes.
-
Replacement of a Dryer Drum in Gütersloh
KDM organized the replacement of two dryer drums, each weighing approximately 250 metric tons, in Gütersloh. The tandem lift and transport within the confined factory grounds were completed within a single day.
-
Laboratory Modules for Wesemann Int. to Malaysia
KDM coordinated the transport of laboratory modules from Blaubeuren to Malaysia on behalf of Wesemann. Temporary storage on the premises bridged the gap until the construction site was completed.