Two Industrial Steam Boilers in Bremen

Two Industrial Steam Boilers in Bremen

Heavy Haulage and Crane Logistics | Bremen | 2017

KDM organized the unloading and installation of two steam boilers in Bremen for Unique Systems. Due to the limited space on the factory grounds, the team had to switch to two compact mobile cranes at short notice to set the boilers down. Both boilers reached their foundations undamaged.

The Project

Our assignment began with unloading the boilers, which had been delivered by inland waterway vessel to the Weserport, and continued through to their placement on the foundations. The two boilers each weighed about 70 metric tons and were moved one after the other across the factory grounds.

The Challenge

Limited space and strict requirements on the factory grounds called for careful coordination. Safety-critical electrical cables ran through the foundation and wall areas. Initially, hydraulic lifting supports were planned for lowering the structure, since the transport platforms were too high for direct positioning.

Our Solution

We organized the unloading from the inland waterway barge and the transport of the boilers using self-propelled modular transport platforms. When the planned hydraulic lifting supports became unavailable at the last minute, we adjusted the procedure and arranged for two city-sized mobile cranes that were as compact as possible. Using these cranes, we were able to place the boilers on their foundations in the confined space.

The result

Both boilers were lowered into place undamaged. The last-minute switch to crane technology made it possible to continue the installation despite the cramped conditions on site.