Two Boilers for the Obernburg Power Plant

Two Boilers for the Obernburg Power Plant

Power Plant Logistics | Obernburg | July 2018

Two boilers had to be installed one on top of the other at the Obernburg power plant. The route ran between two smokestacks at a height of 90 meters and deep into the building. KDM coordinated the logistics all the way down to the foundations. The chosen crane concept significantly reduced the time required for on-site preparation and lifting compared to an alternative proposal.

The Assignment

In July 2018, we handled the logistics for two boilers, from their delivery at the Venlo inland port through to their placement on the foundations at the Obernburg boiler house. The scope of services included temporary storage at the power plant, transport within the plant grounds, and the organization of unloading and installation.

The Challenge

The two boilers were designed to be stacked one on top of the other. To install them, they had to be lifted between two chimneys using a large crane with a 110-meter reach and then lowered 40 meters into the building without the crane operator having a direct line of sight to the landing point. Precise coordination between the crane operator and the signalers was therefore crucial.

An alternative proposal from another provider would have required several weeks for on-site preparation and crane operations. The goal was to find a solution that would combine the challenging lift with a shorter on-site process.

Our Solution

We coordinated the temporary storage and onward transport of the boilers on the factory grounds using self-propelled modular transport (SPMT) platforms. To do this, we arranged for the necessary crane equipment and road closures.

Using the large crane, the boilers were guided between the chimneys. They were then lowered into the boiler house, following the instructions of the guides, until they rested on their designated foundations. The transport and installation were tailored to this unique access situation.

The Result

The boilers were delivered and installed on schedule. The on-site preparation and crane operations were completed within a few days. Compared to the alternative proposal, which would have required several weeks on site, this resulted in significant time and cost savings.