Two Boilers for the Heilbronn Power Plant
Two Boilers for the Heilbronn Power Plant
The Assignment
On Schedule on the Foundation Despite Low Water Levels
KDM organized the logistics for two boilers for SIK Peitz at the power plant site in Heilbronn. The scope of services ranged from pickup at the Aken inland port to placement on the foundations in the boiler house. Following initial coordination in 2023, the logistics project was completed in November 2025.
The Challenge
The agreed-upon date for unloading the boilers was a key prerequisite for the subsequent commissioning. At the same time, low water levels on the Elbe River complicated transportation planning.
In addition to transportation, work on the two boilers had to be integrated into the overall schedule. This required suitable dock space, scaffolding, and service providers who could be mobilized on short notice. At the destination, it was necessary to coordinate the unloading of the ship, the heavy-haul transport, and the weather-dependent installation using a large crane.
The Solution
KDM arranged for storage space in Aken and set up the necessary conditions for sandblasting and coating work, including scaffolding and site planning. To avoid the low-water issue that would have hindered further transport, the boilers were moved to Vahldorf on the Mittelland Canal via a push convoy. There, KDM coordinated the unloading and the continuation of the scaffolding work.
Coordination with the relevant waterway authorities regarding water levels, as well as collaboration with local partners, supported further transportation planning. This also made it possible to organize services needed on short notice.
After the inland waterway transport to Heilbronn, KDM coordinated the unloading, loading onto flatbed trailers, and delivery to the power plant. The scope of services also included organizing the use of a large crane and the necessary road closures, as well as moving the equipment into the boiler house and positioning it on the appropriate foundations.
A single point of contact at KDM oversaw the entire project. Preliminary discussions and on-site visits with our client helped ensure that local conditions were incorporated into the planning at an early stage.
The Result
The two boilers were placed on their foundations by the agreed-upon date. SIK Peitz was thus able to meet the logistical timeline it had committed to with the end customer. The on-time delivery paved the way for the subsequent work and the planned commissioning.